On September 15, the Construction Company completed the factory acceptance and test witnessing of the 110kV combined electrical equipment for the Hongqi Road 220kV Substation Project.



Factory acceptance of equipment is an important guarantee for the smooth commissioning of the project. It directly affects whether the project can be safely and high-quality integrated into the power grid operation. In order to solidly carry out the factory acceptance of materials and equipment, and implement the relevant requirements in the "Notice of State Grid Tianjin Electric Power Company on Further Strengthening and Standardizing Material Quality Supervision Work", several professional and technical backbones from State Grid Tianjin Electric Power Company Maintenance Company and Tianjin Electric Power Engineering Supervision Co., Ltd.,